Lexington Park 69 kV

PJM queue ID AG1-361 Terminal status

Queue IDAG1-361
Project nameLexington Park 69 kV
Status (as published)Withdrawn
SubstationLexington Park
Point of interconnectionLexington Park 69 kV
CountySt. Mary's
StateMD
Voltage69 kV
Capacity2.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity2.7
Mfo20
Withdrawn Date3/16/2021