Substation Scout

Crewe 12.5 kV

PJM queue ID AG1-345 Terminal status

Queue IDAG1-345
Project nameCrewe 12.5 kV
Status (as published)Withdrawn
SubstationCrewe
Point of interconnectionCrewe 12.5 kV
CountyNottoway
StateVA
Voltage12.5 kV
Capacity4.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy8
Mw Capacity4.8
Mfo8
Withdrawn Date10/8/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.