Barterbrook-Stuarts Draft 115 kV

PJM queue ID AG1-325 Terminal status

Queue IDAG1-325
Project nameBarterbrook-Stuarts Draft 115 kV
Status (as published)Withdrawn
SubstationBarterbrook-Stuarts Draft
Point of interconnectionBarterbrook-Stuarts Draft 115 kV
CountyAugusta
StateVA
Voltage115 kV
Capacity26 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2023-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity26
Mfo50
Withdrawn Date3/5/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.