Dresden-Pontiac Midpoint 345 kV

PJM queue ID AG1-321 Terminal status

Queue IDAG1-321
Project nameDresden-Pontiac Midpoint 345 kV
Status (as published)Withdrawn
SubstationDresden-Pontiac Midpoint
Point of interconnectionDresden-Pontiac Midpoint 345 kV
CountyLivingston
StateIL
Voltage345 kV
Capacity126.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-10-01
Source datasetcycle

Additional filed fields

DeveloperCPV Prairie Dock Solar, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy200.0
Mw Capacity126.4
Mfo200.0
Submitted Date9/30/2020
Withdrawn Date6/21/2024
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated6/24/2024