Lake of the Woods DP-Wilderness DP 115 kV

PJM queue ID AG1-289 Terminal status

Queue IDAG1-289
Project nameLake of the Woods DP-Wilderness DP 115 kV
Status (as published)Withdrawn
SubstationLake of the Woods DP-Wilderness DP
Point of interconnectionLake of the Woods DP-Wilderness DP 115 kV
CountyOrange
StateVA
Voltage115 kV
Capacity53.4 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-06-30
Source datasetcycle

Additional filed fields

DeveloperLocust Grove Solar, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy0.0
Mw Capacity53.41
Mfo150.0
Submitted Date9/28/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met