Lake of the Woods DP-Wilderness DP 115 kV
PJM queue ID AG1-289 Terminal status
| Queue ID | AG1-289 |
|---|---|
| Project name | Lake of the Woods DP-Wilderness DP 115 kV |
| Status (as published) | Withdrawn |
| Substation | Lake of the Woods DP-Wilderness DP |
| Point of interconnection | Lake of the Woods DP-Wilderness DP 115 kV |
| County | Orange |
| State | VA |
| Voltage | 115 kV |
| Capacity | 53.4 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2023-06-30 |
| Source dataset | cycle |
Additional filed fields
| Developer | Locust Grove Solar, LLC |
|---|---|
| Transmission Owner | Dominion |
| Project Type | Generation Interconnection |
| Cycle | TC1 |
| Stage | PHASE 1 |
| Mw Energy | 0.0 |
| Mw Capacity | 53.41 |
| Mfo | 150.0 |
| Submitted Date | 9/28/2020 |
| Withdrawn Date | 6/24/2024 |
| Withdrawn Remarks | Customer Milestone Not Met |
| Last Updated | 6/27/2024 |