Stark Solar

PJM queue ID AG1-239 Terminal status

Queue IDAG1-239
Project nameStark Solar
Status (as published)Withdrawn
SubstationBlue Bell-Canton Central
Point of interconnectionBlue Bell-Canton Central 138 kV
CountyStark
StateOH
Voltage138 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity90
Mfo150
Withdrawn Date4/24/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.