Substation Scout

Ramble Wind

PJM queue ID AG1-236 Terminal status

Queue IDAG1-236
Project nameRamble Wind
Status (as published)Withdrawn
SubstationLanesville-Brokaw
Point of interconnectionLanesville-Brokaw 345 kV
CountyLogan
StateIL
Voltage345 kV
Capacity23.4 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2024-12-31
Source datasetcycle

Additional filed fields

DeveloperRamble Wind Energy LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 3
Mw Energy180.0
Mw Capacity23.4
Mfo180.0
Submitted Date9/25/2020
Withdrawn Date11/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated11/4/2025