Springboro 12.47 kV

PJM queue ID AG1-202 Terminal status

Queue IDAG1-202
Project nameSpringboro 12.47 kV
Status (as published)Withdrawn
SubstationSpringboro
Point of interconnectionSpringboro 12.47 kV
CountyCrawford
StatePA
Voltage12.5 kV
Capacity6.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity6.6
Mfo10
Withdrawn Date9/7/2023