Substation Scout

Hadley 12.47 kV

PJM queue ID AG1-201 Terminal status

Queue IDAG1-201
Project nameHadley 12.47 kV
Status (as published)Withdrawn
SubstationHadley
Point of interconnectionHadley 12.47 kV
CountyMercer
StatePA
Voltage12.5 kV
Capacity6.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity6.6
Mfo10
Withdrawn Date11/20/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.