Foster Run
PJM queue ID AG1-193 Terminal status
| Queue ID | AG1-193 |
|---|---|
| Project name | Foster Run |
| Status (as published) | Withdrawn |
| Substation | Utica Junction |
| Point of interconnection | Utica Junction 34.5 kV |
| County | Venango |
| State | PA |
| Voltage | 34.5 kV |
| Capacity | 6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2026-08-28 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 10 |
| Mw Capacity | 6 |
| Mfo | 10 |
| Withdrawn Date | 12/11/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.