Carson-Suffolk 500 kV

PJM queue ID AG1-184 Terminal status

Queue IDAG1-184
Project nameCarson-Suffolk 500 kV
Status (as published)Withdrawn
SubstationCarson-Suffolk
Point of interconnectionCarson-Suffolk 500 kV
CountySussex
StateVA
Voltage500 kV
Capacity175.1 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-06-30
Source datasetcycle

Additional filed fields

DeveloperCabin Point Solar, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy0.0
Mw Capacity175.06
Mfo500.0
Submitted Date9/17/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024