Substation Scout

Hopewell-Surry 230 kV

PJM queue ID AG1-174 Terminal status

Queue IDAG1-174
Project nameHopewell-Surry 230 kV
Status (as published)Withdrawn
SubstationHopewell-Surry
Point of interconnectionHopewell-Surry 230 kV
CountySurry
StateVA
Voltage230 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-10-15
Source datasetcycle

Additional filed fields

DeveloperSR-Colonial Trail LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy20.0
Mw Capacity12.0
Mfo20.0
Submitted Date9/16/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.