Wattsville 69 kV II

PJM queue ID AG1-150 Terminal status

Queue IDAG1-150
Project nameWattsville 69 kV II
Status (as published)Withdrawn
SubstationWattsville II
Point of interconnectionWattsville 69 kV II
CountyAccomack
StateVA
Voltage69 kV
Capacity40 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2021-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy40
Mw Capacity40
Mfo80
Withdrawn Date9/12/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.