Substation Scout

North Anna-Ladysmith 500 kV

PJM queue ID AG1-133 Terminal status

Queue IDAG1-133
Project nameNorth Anna-Ladysmith 500 kV
Status (as published)Withdrawn
SubstationNorth Anna-Ladysmith
Point of interconnectionNorth Anna-Ladysmith 500 kV
CountySpotsylvania
StateVA
Voltage500 kV
Capacity76.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-01
Source datasetcycle

Additional filed fields

DeveloperVirginia Electric and Power Company
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy128.0
Mw Capacity76.8
Mfo128.0
Submitted Date9/2/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.