Substation Scout

Churchtown-Upper Pittsgrove 138 kV

PJM queue ID AG1-117 Terminal status

Queue IDAG1-117
Project nameChurchtown-Upper Pittsgrove 138 kV
Status (as published)Withdrawn
SubstationChurchtown-Upper Pittsgrove
Point of interconnectionChurchtown-Upper Pittsgrove 138 kV
CountySalem
StateNJ
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2021-12-03
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity0
Mfo149.3
Withdrawn Date6/28/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.