Substation Scout

Chapel Energy Storage Facility

PJM queue ID AG1-104 Terminal status

Queue IDAG1-104
Project nameChapel Energy Storage Facility
Status (as published)Withdrawn
SubstationWaugh Chapel
Point of interconnectionWaugh Chapel 230 kV
CountyAnne Arundel
StateMD
Voltage230 kV
Capacity120 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy300
Mw Capacity120
Mfo300
Withdrawn Date11/7/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.