Substation Scout

Gloucester Solar I

PJM queue ID AG1-103 Terminal status

Queue IDAG1-103
Project nameGloucester Solar I
Status (as published)Withdrawn
SubstationClayton-Williamstown
Point of interconnectionClayton-Williamstown 69 kV
CountyGloucester
StateNJ
Voltage69 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity0
Mfo44
Withdrawn Date3/18/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.