Oakland-Gorman 69 kV

PJM queue ID AG1-101 Terminal status

Queue IDAG1-101
Project nameOakland-Gorman 69 kV
Status (as published)Withdrawn
SubstationOakland-Gorman
Point of interconnectionOakland-Gorman 69 kV
CountyGarrett
StateMD
Voltage69 kV
Capacity6.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity6.7
Mfo20
Withdrawn Date9/5/2023