NC1 Ahoskie Central Solar Project

PJM queue ID AG1-082 Terminal status

Queue IDAG1-082
Project nameNC1 Ahoskie Central Solar Project
Status (as published)Withdrawn
SubstationAhoskie
Point of interconnectionAhoskie 34.5 kV
CountyHertford
StateNC
Voltage34.5 kV
Capacity12 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2021-12-31
Source datasetcycle

Additional filed fields

DeveloperNC1 Ahoskie Central, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 3
Mw Energy20.0
Mw Capacity12.0
Mfo20.0
Submitted Date7/31/2020
Withdrawn Date11/3/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated11/3/2025