Substation Scout

Wood Duck 100 MW

PJM queue ID AG1-071 Terminal status

Queue IDAG1-071
Project nameWood Duck 100 MW
Status (as published)Withdrawn
SubstationBon Ayr
Point of interconnectionBon Ayr 69 kV
CountyBarren
StateKY
Voltage69 kV
Capacity37.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-06-01
Source datasetcycle

Additional filed fields

DeveloperWood Duck Solar LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 3
Mw Energy55.0
Mw Capacity37.5
Mfo100.0
Submitted Date7/30/2020
Withdrawn Date11/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated11/3/2025