PJM queue ID AG1-065 Terminal status

Queue IDAG1-065
Project nameBermuda Energy
Status (as published)Withdrawn
SubstationPlaza
Point of interconnectionPlaza 34.5 kV
CountyCity of Richmond
StateVA
Voltage34.5 kV
Capacity8 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-12-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.1
Mw Capacity8
Mfo19.1
Withdrawn Date6/24/2022