Substation Scout

Stryker-Ridgeville 138 kV

PJM queue ID AG1-056 Terminal status

Queue IDAG1-056
Project nameStryker-Ridgeville 138 kV
Status (as published)Withdrawn
SubstationStryker-Ridgeville
Point of interconnectionStryker-Ridgeville 138 kV
CountyWilliams
StateOH
Voltage138 kV
Capacity32.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy54
Mw Capacity32.4
Mfo202
Withdrawn Date2/26/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.