Substation Scout

Maysville 69 kV III

PJM queue ID AG1-051 Terminal status

Queue IDAG1-051
Project nameMaysville 69 kV III
Status (as published)Withdrawn
SubstationMaysville III
Point of interconnectionMaysville 69 kV III
CountyMercer
StatePA
Voltage69 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-06-30
Source datasetcycle

Additional filed fields

DeveloperMC Solar, LLC
Transmission OwnerATSI
Project TypeGeneration Interconnection
CycleTC1
StageDP1
Mw Energy20.0
Mw Capacity20.0
Mfo70.0
Submitted Date7/18/2020
Withdrawn Date7/18/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated1/29/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.