Maysville 69 kV III
PJM queue ID AG1-051 Terminal status
| Queue ID | AG1-051 |
|---|---|
| Project name | Maysville 69 kV III |
| Status (as published) | Withdrawn |
| Substation | Maysville III |
| Point of interconnection | Maysville 69 kV III |
| County | Mercer |
| State | PA |
| Voltage | 69 kV |
| Capacity | 20 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2022-06-30 |
| Source dataset | cycle |
Additional filed fields
| Developer | MC Solar, LLC |
|---|---|
| Transmission Owner | ATSI |
| Project Type | Generation Interconnection |
| Cycle | TC1 |
| Stage | DP1 |
| Mw Energy | 20.0 |
| Mw Capacity | 20.0 |
| Mfo | 70.0 |
| Submitted Date | 7/18/2020 |
| Withdrawn Date | 7/18/2024 |
| Withdrawn Remarks | Customer Milestone Not Met |
| Last Updated | 1/29/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.