PJM queue ID AG1-046 Terminal status

Queue IDAG1-046
Project nameFreeport 138 kV
Status (as published)Withdrawn
SubstationFreeport
Point of interconnectionFreeport 138 kV
CountyNot reported
StateNot reported
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2020-07-06
Source datasetserial

Additional filed fields

Project TypeUpgrade Request
Withdrawn Date8/27/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.