Hayden 345 kV

PJM queue ID AG1-042 Terminal status

Queue IDAG1-042
Project nameHayden 345 kV
Status (as published)Withdrawn
SubstationHayden
Point of interconnectionHayden 345 kV
CountyFranklin
StateOH
Voltage345 kV
Capacity66.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity66.9
Mfo100
Withdrawn Date8/19/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.