Substation Scout

Weirton Solar 24 kV

PJM queue ID AG1-029 Terminal status

Queue IDAG1-029
Project nameWeirton Solar 24 kV
Status (as published)Withdrawn
SubstationWeirton Solar
Point of interconnectionWeirton Solar 24 kV
CountyHancock
StateWV
Voltage24 kV
Capacity13.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-10-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy30
Mw Capacity13.6
Mfo30
Withdrawn Date9/15/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.