Substation Scout

Arnold's Corner-Dahlgren 230 kV

PJM queue ID AG1-019 Terminal status

Queue IDAG1-019
Project nameArnold's Corner-Dahlgren 230 kV
Status (as published)Withdrawn
SubstationArnold's Corner-Dahlgren
Point of interconnectionArnold's Corner-Dahlgren 230 kV
CountyKing George
StateVA
Voltage230 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-10-31
Source datasetcycle

Additional filed fields

DeveloperHarwood Power, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy100.0
Mw Capacity100.0
Mfo200.0
Submitted Date5/20/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.