Santos Solar

PJM queue ID AG1-001 Terminal status

Queue IDAG1-001
Project nameSantos Solar
Status (as published)Withdrawn
SubstationUS Silica-Unimin
Point of interconnectionUS Silica-Unimin 69 kV
CountyCumberland
StateNJ
Voltage69 kV
Capacity11.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-03-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy31
Mw Capacity11.78
Mfo31
Withdrawn Date1/10/2025