Reed-Reed Tap #2 69 kV

PJM queue ID AF2-444 Terminal status

Queue IDAF2-444
Project nameReed-Reed Tap #2 69 kV
Status (as published)Withdrawn
SubstationReed-Reed Tap #2
Point of interconnectionReed-Reed Tap #2 69 kV
CountyNorthumberland
StatePA
Voltage69 kV
Capacity11.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.8
Mw Capacity11.8
Mfo19.8
Withdrawn Date12/18/2024