Substation Scout

Vernon 115 kV

PJM queue ID AF2-443 Terminal status

Queue IDAF2-443
Project nameVernon 115 kV
Status (as published)Withdrawn
SubstationVernon
Point of interconnectionVernon 115 kV
CountySussex
StateNJ
Voltage115 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2023-05-31
Source datasetserial

Additional filed fields

Project TypeMerchant Transmission
Mw Energy84
Mw Capacity0
Mfo84
Withdrawn Date7/25/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.