Substation Scout

Fike Solar

PJM queue ID AF2-398 Terminal status

Queue IDAF2-398
Project nameFike Solar
Status (as published)Withdrawn
SubstationNecessity-Dinnerbell
Point of interconnectionNecessity-Dinnerbell 12.47 kV
CountyFayette
StatePA
Voltage12.5 kV
Capacity1.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3
Mw Capacity1.9
Mfo3
Withdrawn Date10/8/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.