Substation Scout

Nelson 69 kV

PJM queue ID AF2-385 Terminal status

Queue IDAF2-385
Project nameNelson 69 kV
Status (as published)Withdrawn
SubstationNelson
Point of interconnectionNelson 69 kV
CountySussex
StateDE
Voltage69 kV
Capacity47.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-10-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy75
Mw Capacity47.8
Mfo75
Withdrawn Date10/14/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.