Substation Scout

Royerton Solar and Storage

PJM queue ID AF2-370 Terminal status

Queue IDAF2-370
Project nameRoyerton Solar and Storage
Status (as published)Withdrawn
SubstationDelaware-Royerton
Point of interconnectionDelaware-Royerton 138 kV
CountyDelaware
StateIN
Voltage138 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-12-31
Source datasetcycle

Additional filed fields

DeveloperRoyerton Solar, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 3
Mw Energy0.0
Mw Capacity20.0
Mfo100.0
Submitted Date3/31/2020
Withdrawn Date11/4/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated1/30/2026