West Gerrard-J.K. Smith 345 kV
PJM queue ID AF2-355 Terminal status
| Queue ID | AF2-355 |
|---|---|
| Project name | West Gerrard-J.K. Smith 345 kV |
| Status (as published) | Withdrawn |
| Substation | West Gerrard-J.K. Smith |
| Point of interconnection | West Gerrard-J.K. Smith 345 kV |
| County | Madison |
| State | KY |
| Voltage | 345 kV |
| Capacity | 135 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2022-07-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | AEUG Richmond Solar, LLC |
|---|---|
| Transmission Owner | EKPC |
| Project Type | Generation Interconnection |
| Cycle | TC1 |
| Stage | DP2 |
| Mw Energy | 225.0 |
| Mw Capacity | 135.0 |
| Mfo | 225.0 |
| Submitted Date | 3/31/2020 |
| Withdrawn Date | 1/22/2025 |
| Withdrawn Remarks | Customer Milestone Not Met |
| Last Updated | 9/22/2025 |