Bowling Green 2-Tontogony 69 kV
PJM queue ID AF2-347 Terminal status
| Queue ID | AF2-347 |
|---|---|
| Project name | Bowling Green 2-Tontogony 69 kV |
| Status (as published) | Withdrawn |
| Substation | Bowling Green 2-Tontogony |
| Point of interconnection | Bowling Green 2-Tontogony 69 kV |
| County | Not reported |
| State | Not reported |
| Voltage | 69 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Not reported |
| Resource category | Not reported (normalised for filtering) |
| Target commercial operation | 2020-03-30 |
| Source dataset | serial |
Additional filed fields
| Project Type | Upgrade Request |
|---|---|
| Withdrawn Date | 9/28/2020 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.