Substation Scout

Sandwich-Plano 138 kV

PJM queue ID AF2-329 Terminal status

Queue IDAF2-329
Project nameSandwich-Plano 138 kV
Status (as published)Withdrawn
SubstationSandwich-Plano
Point of interconnectionSandwich-Plano 138 kV
CountyKendall
StateIL
Voltage138 kV
Capacity42.2 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-12-01
Source datasetcycle

Additional filed fields

DeveloperPlano Skies Energy Center, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 2
Mw Energy42.2
Mw Capacity42.2
Mfo292.2
Submitted Date3/30/2020
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated1/27/2025