Substation Scout

Susquehanna Unit 2 500 kV

PJM queue ID AF2-315 Terminal status

Queue IDAF2-315
Project nameSusquehanna Unit 2 500 kV
Status (as published)Withdrawn
SubstationSusquehanna Unit 2
Point of interconnectionSusquehanna Unit 2 500 kV
CountyLuzerne
StatePA
Voltage500 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Nuclear
Resource categoryNuclear (normalised for filtering)
Target commercial operation2020-08-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity0
Mfo1310
Withdrawn Date11/30/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.