Central Hardin-Stephensburg 69 kV

PJM queue ID AF2-309 Terminal status

Queue IDAF2-309
Project nameCentral Hardin-Stephensburg 69 kV
Status (as published)Withdrawn
SubstationCentral Hardin-Stephensburg
Point of interconnectionCentral Hardin-Stephensburg 69 kV
CountyHardin
StateKY
Voltage69 kV
Capacity42 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy70
Mw Capacity42
Mfo70
Withdrawn Date10/14/2024