Substation Scout

Flat Top Solar

PJM queue ID AF2-306 Terminal status

Queue IDAF2-306
Project nameFlat Top Solar
Status (as published)Withdrawn
SubstationHope-Blevins Valley Tap
Point of interconnectionHope-Blevins Valley Tap 69 kV
CountyBarren
StateKY
Voltage69 kV
Capacity26 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy26
Mw Capacity26
Mfo26
Withdrawn Date4/10/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.