Substation Scout

CT-Industrial Park

PJM queue ID AF2-293 Terminal status

Queue IDAF2-293
Project nameCT-Industrial Park
Status (as published)Withdrawn
SubstationBeech Creek
Point of interconnectionBeech Creek 12.47 kV
CountyClinton
StatePA
Voltage12.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2026-04-09
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.17
Mw Capacity0
Mfo1.17
Withdrawn Date3/11/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.