Big Pond Solar Power Plant

PJM queue ID AF2-265 Terminal status

Queue IDAF2-265
Project nameBig Pond Solar Power Plant
Status (as published)Withdrawn
SubstationSouth Troy-Athens
Point of interconnectionSouth Troy-Athens 34.5 kV
CountyBradford
StatePA
Voltage34.5 kV
Capacity8.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-09-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy15
Mw Capacity8.6
Mfo15
Withdrawn Date8/29/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.