Substation Scout

Stephensburg-Central Hardin 69 kV

PJM queue ID AF2-260 Terminal status

Queue IDAF2-260
Project nameStephensburg-Central Hardin 69 kV
Status (as published)Withdrawn
SubstationStephensburg-Central Hardin
Point of interconnectionStephensburg-Central Hardin 69 kV
CountyHardin
StateKY
Voltage69 kV
Capacity53 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy85
Mw Capacity53
Mfo85
Withdrawn Date4/7/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.