Substation Scout

Bradley Ridge Solar

PJM queue ID AF2-255 Terminal status

Queue IDAF2-255
Project nameBradley Ridge Solar
Status (as published)Withdrawn
SubstationIron Bridge
Point of interconnectionIron Bridge 34.5 kV
CountyChesterfield
StateVA
Voltage34.5 kV
Capacity3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity3
Mfo25
Withdrawn Date5/19/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.