Substation Scout

Powhatan 34.5 kV

PJM queue ID AF2-244 Terminal status

Queue IDAF2-244
Project namePowhatan 34.5 kV
Status (as published)Withdrawn
SubstationPowhatan
Point of interconnectionPowhatan 34.5 kV
CountyPowhatan
StateVA
Voltage34.5 kV
Capacity9.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy15
Mw Capacity9.4
Mfo15
Withdrawn Date1/6/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.