Substation Scout

Wharton 115 kV

PJM queue ID AF2-242 Terminal status

Queue IDAF2-242
Project nameWharton 115 kV
Status (as published)Withdrawn
SubstationWharton
Point of interconnectionWharton 115 kV
CountyBeaufort
StateNC
Voltage115 kV
Capacity45 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity45
Mfo80
Withdrawn Date3/25/2021

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.