Union City-Cambridge Springs 34.5 kV
PJM queue ID AF2-237 Terminal status
| Queue ID | AF2-237 |
|---|---|
| Project name | Union City-Cambridge Springs 34.5 kV |
| Status (as published) | Withdrawn |
| Substation | Union City-Cambridge Springs |
| Point of interconnection | Union City-Cambridge Springs 34.5 kV |
| County | Crawford |
| State | PA |
| Voltage | 34.5 kV |
| Capacity | 6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2023-01-01 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 10 |
| Mw Capacity | 6 |
| Mfo | 30 |
| Withdrawn Date | 9/14/2020 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.