Substation Scout

Big Bell Solar

PJM queue ID AF2-235 Terminal status

Queue IDAF2-235
Project nameBig Bell Solar
Status (as published)Withdrawn
SubstationTitusville-Oil Creek
Point of interconnectionTitusville-Oil Creek 34.5 kV
CountyCrawford
StatePA
Voltage34.5 kV
Capacity6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-07-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity6
Mfo10
Withdrawn Date8/28/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.