Substation Scout

Heartsease DP-Anaconda 115 kV

PJM queue ID AF2-214 Terminal status

Queue IDAF2-214
Project nameHeartsease DP-Anaconda 115 kV
Status (as published)Withdrawn
SubstationHeartsease DP-Anaconda
Point of interconnectionHeartsease DP-Anaconda 115 kV
CountyEdgecombe
StateNC
Voltage115 kV
Capacity60.5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-12-02
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy151.2
Mw Capacity60.5
Mfo151.2
Withdrawn Date8/24/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.