Lena - Lancaster 138 kV

PJM queue ID AF2-201 Terminal status

Queue IDAF2-201
Project nameLena - Lancaster 138 kV
Status (as published)Withdrawn
SubstationLena - Lancaster
Point of interconnectionLena - Lancaster 138 kV
CountyStephenson
StateIL
Voltage138 kV
Capacity51.4 MW
Resource (as published)Wind,Solar,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2023-05-31
Source datasetcycle

Additional filed fields

DeveloperBlue Violet Energy, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 2
Mw Energy199.0
Mw Capacity51.4
Mfo199.0
Submitted Date3/24/2020
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated1/27/2025