Substation Scout

Nelson-Lee County 345 kV

PJM queue ID AF2-183 Terminal status

Queue IDAF2-183
Project nameNelson-Lee County 345 kV
Status (as published)Withdrawn
SubstationNelson-Lee County
Point of interconnectionNelson-Lee County 345 kV
CountyLee
StateIL
Voltage345 kV
Capacity32 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-12-01
Source datasetcycle

Additional filed fields

DeveloperDeriva Energy Solar, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy80.0
Mw Capacity32.0
Mfo600.0
Submitted Date3/20/2020
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024